Audit Instruments (1)

Q1Easy
Which of the following instruments are correctly matched with their use in an Energy Audit?
1. Lux Meter: Measuring illumination levels.
2. Ultrasonic Flow Meter: Measuring liquid flow in pipes without cutting them.
3. Combustion Analyzer: Measuring the power factor of electric motors.
Select the correct answer:
View answer & solution
Correct answer: A. 1 and 2 only
Quick explanation

Energy management begins by establishing where and how energy is used. Energy intensity normalizes energy use by useful output, such as kWh per unit of production. Key relation: Energy intensity=energy consumed/useful production output.

Exam focus: Normalize energy use before comparing production periods. Common trap: A detailed audit is not just a more detailed desk review; it includes measurements.

Energy intensity=energy consumed/useful production output.
Verified · SRO editorial deskSolution page → Report

Audit Types and Metrics (1)

Q2Moderate
Regarding Energy Management and Audit, consider the following:
1. A "Preliminary Audit" uses existing data to establish energy consumption patterns.
2. A "Detailed Audit" involves the use of instruments to measure energy flow in specific equipment.
3. The "Energy Intensity" of a product is the ratio of total energy consumed to the total units of production.
Which of the statements given above is/are correct?
View answer & solution
Correct answer: C. 1, 2 and 3
Quick explanation

A preliminary/walk-through audit uses bills, production data and observations to identify major opportunities; a detailed audit adds instrumented measurements and engineering calculations. Energy intensity normalizes energy use by useful output, such as kWh per unit of production. Key relation: Energy intensity=energy consumed/useful production output.

Exam focus: Normalize energy use before comparing production periods. Common trap: A detailed audit is not just a more detailed desk review; it includes measurements.

Energy intensity=energy consumed/useful production output.
Verified · SRO editorial deskSolution page → Report

Payback Period (1)

Q3Moderate
Consider the following statements regarding the "Payback Period" in energy projects:
1. It is the time taken for the cumulative energy savings to equal the initial investment.
2. A shorter payback period indicates a more financially attractive project.
3. Simple Payback Period (SPP) accounts for the "Time Value of Money"Which of the statements given above is/are correct?
View answer & solution
Correct answer: B. 1 and 2 only
Quick explanation

Simple payback is easy and useful for first screening, but it is not a complete profitability measure. Discounted payback, NPV and IRR address time value more explicitly. Key relation: If annual savings are uniform: SPP = Initial investment / Annual net savings. Discounted methods use PV = CF_t/(1+r)^t.

Exam focus: Whenever a question says “simple payback”, immediately remember “no time value of money”. Common trap: Confusing simple payback with discounted payback or NPV.

If annual savings are uniform: SPP = Initial investment / Annual net savings. Discounted methods use PV = CFt/(1+r)^t.