This question was asked inGPSC Deputy Executive Engineer (Electrical) Class-2 Master Paper 2026Question 190 of 195 published · Gujarat Public Service CommissionOpen paper
Q190ModerateElectricity Act & Regulation

Consider the following statements regarding the "Cross-Subsidy Surcharge":
1. It is payable by consumers who opt for open access.
2. It is intended to compensate the distribution licensee for the loss of cross-subsidy.
3. The State Commission has no power to reduce or eliminate this surchargeWhich of the statements given above is/are correct?

Answer & step-by-step solution
Correct answer: B. 1 and 2 only
Quick explanation

State Commissions have a central role in introducing and regulating distribution-level open access and associated charges. Cross-subsidy surcharge compensates the incumbent distribution licensee for loss of cross-subsidy and is determined/reduced under the regulatory framework. Key relation: Open access charges may include transmission/wheeling, cross-subsidy and other applicable charges.

Exam focus: Open access is not limited to a Central Transmission Utility. Common trap: The State Commission does have regulatory authority over surcharge treatment.

Statement-wise Verification

  • Statement 1 - Correct.
    It is payable by consumers who opt for open access.
    Open access is not limited to a Central Transmission Utility.
  • Statement 2 - Correct.
    It is intended to compensate the distribution licensee for the loss of cross-subsidy.
    Cross-subsidy surcharge compensates the incumbent distribution licensee for loss of cross-subsidy and is determined/reduced under the regulatory framework.
  • Statement 3 - Incorrect.
    The State Commission has no power to reduce or eliminate this surcharge
    The surcharge is determined within the statutory/regulatory framework and is subject to Commission-specified treatment/reduction; the Commission is not powerless

Core Concept

The Electricity Act defines open access as non-discriminatory use of transmission lines or distribution systems by eligible users in accordance with regulations. State Commissions have a central role in introducing and regulating distribution-level open access and associated charges. Cross-subsidy surcharge compensates the incumbent distribution licensee for loss of cross-subsidy and is determined/reduced under the regulatory framework.

Formula / Key Relationship

Open access charges may include transmission/wheeling, cross-subsidy and other applicable charges.

Why the Other Options Are Wrong

Option A is incorrect because it includes incorrect statement(s) 3 and omits correct statement(s) 1. Option C is incorrect because it omits correct statement(s) 2. Option D is incorrect because it includes incorrect statement(s) 3.

Exam Shortcut / Approach

Open access is not limited to a Central Transmission Utility.

Common Mistake

The State Commission does have regulatory authority over surcharge treatment.

Quick Revision

Purpose and Regulatory Control is linked with Cross-Subsidy Surcharge, Open Access Charges and Electricity Law and Regulation. Open access is not limited to a Central Transmission Utility.

Exam tipOpen access is not limited to a Central Transmission Utility.
Verified · SRO editorial desk Report