This question was asked inGPSC Deputy Executive Engineer (Electrical) Class-2 Master Paper 2026Question 187 of 195 published · Gujarat Public Service CommissionOpen paper
Q187ModerateRenewable Energy Policy

Consider the following statements regarding the Gujarat Small Hydel Policy:
1. Small hydel projects are typically classified for capacities up to 25 MW.
2. Hydropower projects are considered “must-run” sources and are given priority in grid dispatch.
3. Tariff determination for small hydel projects is carried out by the State Electricity Regulatory Commission.
Which of the statements given above is/are correct?

Answer & step-by-step solution
Correct answer: C. 1 and 3 only
Quick explanation

Small-hydropower questions combine capacity classification, grid-dispatch treatment and tariff regulation. In India, 'small hydro' is commonly associated with projects up to 25 MW, while tariff and scheduling treatment is governed by the relevant electricity commission/regulations. Key relation: Hydro power P≈ρgQHη.

Exam focus: Keep capacity definition, dispatch status and tariff authority as separate statements. Common trap: Do not assume every renewable technology has identical scheduling treatment.

Statement-wise Verification

  • Statement 1 - Correct.
    Small hydel projects are typically classified for capacities up to 25 MW.
    In India, 'small hydro' is commonly associated with projects up to 25 MW
  • Statement 2 - Incorrect.
    Hydropower projects are considered “must-run” sources and are given priority in grid dispatch.
    The correct principle is: Small-hydropower questions combine capacity classification, grid-dispatch treatment and tariff regulation.
  • Statement 3 - Correct.
    Tariff determination for small hydel projects is carried out by the State Electricity Regulatory Commission.
    In India, 'small hydro' is commonly associated with projects up to 25 MW, while tariff and scheduling treatment is governed by the relevant electricity commission/regulations.

Core Concept

Small-hydropower questions combine capacity classification, grid-dispatch treatment and tariff regulation. In India, 'small hydro' is commonly associated with projects up to 25 MW, while tariff and scheduling treatment is governed by the relevant electricity commission/regulations. Exact must-run provisions should be tied to the applicable policy/order.

Formula / Key Relationship

Hydro power P≈ρgQHη.

Why the Other Options Are Wrong

Option A is incorrect because it includes incorrect statement(s) 2 and omits correct statement(s) 3. Option B is incorrect because it includes incorrect statement(s) 2 and omits correct statement(s) 1. Option D is incorrect because it includes incorrect statement(s) 2.

Exam Shortcut / Approach

Keep capacity definition, dispatch status and tariff authority as separate statements.

Common Mistake

Do not assume every renewable technology has identical scheduling treatment.

Quick Revision

Capacity Classification and Tariff is linked with Small Hydel Policy, Small Hydro and Renewable Energy Policy. Keep capacity definition, dispatch status and tariff authority as separate statements.

Exam tipKeep capacity definition, dispatch status and tariff authority as separate statements.